South Korea plans to exempt artificial intelligence data centers outside the Seoul metropolitan area from electricity grid impact assessments if their contracted power capacity is 50 megawatts (MW) or less, under regulatory changes announced Nov. 20 by the Ministry of Science and ICT and the Ministry of Climate, Energy and Environment.
The proposal is part of a broader effort to accelerate construction of AI data centers while maintaining electricity grid stability. The government outlined three measures: exemptions for smaller regional facilities, simplified assessments in designated data center zones and priority reviews for large-scale projects.
Regional facilities to receive exemptions
Under the proposed enforcement decree of South Korea's Special Act on the Promotion of the Artificial Intelligence Data Center Industry, newly built, expanded or converted data centers outside the capital region with contracted power capacity of 50 MW or less would be exempt from power grid impact assessments.
The government said it selected the threshold after considering industry requests and the potential effects of large data centers on regional electricity networks. The decree was formally submitted for public comment on Nov. 20.
Officials said raising the exemption threshold to 100 MW would still leave most gigawatt-scale mega-projects outside the exemption. They also noted that operators spend considerable time preparing for nontechnical assessment requirements, prompting the government to pursue broader procedural changes.
Simplified reviews in designated data center zones
Facilities located in designated AI data center zones would be exempt from nontechnical assessment requirements regardless of size. They would still undergo technical reviews examining their impact on the electricity grid. The scoring criteria for electricity demand in those technical assessments could also be adjusted.
The climate ministry plans to revise its administrative rules governing power grid impact assessments. The special act also calls for linking designated data center zones with distributed energy special zones, which are intended to support localized energy production and consumption. Some existing demand-attraction distributed energy zones already receive exemptions from nontechnical assessments.
Priority reviews for major projects
Large-scale data center developments classified as mega-projects, as well as facilities applying for consolidated permitting under the special act, would receive priority assessment regardless of their capacity.
The climate ministry plans to incorporate priority-review provisions into a forthcoming assessment manual. The measure is intended to reduce waiting times for grid evaluations and help developers begin construction sooner.
The Special Act on the Promotion of the Artificial Intelligence Data Center Industry is scheduled to take effect March 10, 2027. The two ministries said they would complete the necessary regulatory revisions and operational guidelines ahead of its implementation, balancing faster construction with electricity grid reliability.